A contractor employed some men to complete a work which can be done by 80 men in 70 days at the end of 25 days 35 men left the work and 15 days later half of the remainder left and the work got finished 5 days later. Find the number of men originally employed
Answers
Answered by
1
Answer:
80 men were originally employed.
Step-by-step explanation:
it asked how many men he originally started with not how many at the end. so he originally employed 80 men.