a contractor employs
360 man who can finish a certain piece of work in 11 months how many extra men must be employed to complete the job in 9 months
Answers
Answered by
11
Answer:
men. time
360. 11 months
x. 9 months
x = 11x360/9=440 men ( Total)
Extramen required=440-360=80 men. Ans