a contractor employs
360 man who can finish a certain piece of work in 11 months how many extra men must be employed to complete the job in 9 months

Answers

Answered by haridasan85
11

Answer:

men. time

360. 11 months

x. 9 months

x = 11x360/9=440 men ( Total)

Extramen required=440-360=80 men. Ans