Math, asked by jtsydudjgfjf7661, 1 year ago

A contractor employs 360 men who can finish a certain piece of work in 11 months. How many more men must be employed to complete the work in 9 months?

Answers

Answered by JeanaShupp
59

Answer: 80 men should be employed more to complete the work in 9 months

Step-by-step explanation:

Men                                    360                       x

Time(in months)                11                          9

As it is inversely related

therefore we have

360\times 11= x\times 9 \\\\\Rightarrow x=\dfrac{360\times 11}{9} = 440

Men should be employed more= 440 -360 = 80

Hence, 80 men should be employed more to complete the work in 9 months

Answered by khushikumar8080
7

Answer:

here is your answer

mark in the top

Attachments:
Similar questions