A contractor employs 360 men who can finish a certain piece of work in 11 months. How many more men must be employed to complete the work in 9 months?
Answers
Answered by
59
Answer: 80 men should be employed more to complete the work in 9 months
Step-by-step explanation:
Men 360 x
Time(in months) 11 9
As it is inversely related
therefore we have
Men should be employed more= 440 -360 = 80
Hence, 80 men should be employed more to complete the work in 9 months