a contractor employs 40 men to do a piece of work in 60 days each man working 9 hours a day he is then requested to do the job in 48 days how many more men working 10 hours a day does he need to employ
Answers
Answered by
3
Answer:
45
Step-by-step explanation:
total man hours initially = 40*60*9=21600 man-hours.
new hours = 48*10=480 hrs
new men required=21600/480=45
Similar questions
Math,
6 months ago
Math,
6 months ago
World Languages,
6 months ago
English,
1 year ago
Economy,
1 year ago