A contractor employs 56 laborers to lay a road. He agrees to get the work done in 15 days. But the authorities want the work to be completed in 10 days. How many more men should he employ?
Answers
Answered by
4
Answer: 28 more men he should employ.
Step-by-step explanation:
Since we have given that
Number of laborers to lay a road = 56
Number of days it requires = 15
If the number of days it required = 10
So, we need to find the number of laborers.
According to question, it becomes,
56 * 10 = 15 * x
840 = 10x
x = 840/10
x = 84
Hence, 84-56 = 28 more men he should employ.