Math, asked by devilrakshitraj, 4 days ago

A contractor employs 56 labourers to lay a road. He agrees to get the work done in 15 days. But the authorities want the work to be completed in 10 days. How many more men should he employ?​

Answers

Answered by stbranham2007
1

56 * 15 = 10 * x

840 = 10x

x = 840/10

x = 84

84 - 56 = 28

Answered by prasenjeetbehera
0

Answer

Step-by-step explanation:

  1. 1 man can do the work=56×15 days=840 days
  2. Men needed to do the work in 10 days =840÷10=84 day
  3. More men needed= 84-56=28 men
  4. Therefore, 28 more men are needed to do the work in 10 days
  5. I hope it helps you friend.