A contractor employs 56 labourers to lay a road. He agrees to get the work done in 15 days. But the authorities want the work to be completed in 10 days. How many more men should he employ?
Answers
Answered by
1
56 * 15 = 10 * x
840 = 10x
x = 840/10
x = 84
84 - 56 = 28
Answered by
0
Answer
Step-by-step explanation:
- 1 man can do the work=56×15 days=840 days
- Men needed to do the work in 10 days =840÷10=84 day
- More men needed= 84-56=28 men
- Therefore, 28 more men are needed to do the work in 10 days
- I hope it helps you friend.