A contractor employs 64 workers to lay a road. He agrees to complete the work in
18 days. But if the authorities want the work to be completed in 8 days, how many more
workers should he employ?
Inverse proportion question.
Answer fast. if who answers first I will mark as brainlist.
Answers
Answered by
0
Step-by-step explanation:
Since we have given that
Number of labourers to lay a road = 56
Number of days it requires = 15
If the number of days it required = 10
So, we need to find the number of labourers.
According to question, it becomes,
\begin{gathered}56\times 15=10\times x\\\\840=10x\\\\x=\dfrac{840}{10}\\\\x=84\end{gathered}
56×15=10×x
840=10x
x=
10
840
x=84
Hence, 84-56 = 28 more men he should employ.
Similar questions