Math, asked by 2005100120, 3 months ago

A contractor employs 64 workers to lay a road. He agrees to complete the work in
18 days. But if the authorities want the work to be completed in 8 days, how many more
workers should he employ?
Inverse proportion question.
Answer fast. if who answers first I will mark as brainlist.​

Answers

Answered by zunairahfarid07
0

Answer:

18days------------------------64labours

8days------------------------??

(18/8)*64=144labours

No. of workers more = 144-64 = 80

Similar questions