A contractor employs a work force of 600 men to complete a project in 8 months. He was asked to complete the work in 6 months. How many extra workers should he employ?​

Answers

Answered by sheetalbhateja89891
0

Answer:

please tell me which answer u want

Answered by farhaanaarif84
1

Answer:

Men Time

420 9 months

x 7 months

As the number of workers is inversely proportional to time taken:

420×9=x×7⟹x=

7

420×9

=540

∴ extra men needed: 540−420=120