A contractor estimated that his team of 15 men can construct a bridge in 100 days if there was no rain. (Assume the team does work on rainy day and rain is the only factor that can deter the team from working). However, on 51st day, after 5 days of rain, he hired 5 more people and finished the project early. If the job was done in; days, how many days after day 50 had rain?
A) 6
B) 8
C) 9
D) 5
Answers
Answered by
1
The answer is 5.
Hope this answer helps you .
Please mark me as brainliest.
Similar questions
English,
6 months ago
Math,
6 months ago
English,
6 months ago
Biology,
1 year ago
Social Sciences,
1 year ago
Physics,
1 year ago
Social Sciences,
1 year ago