A contractor estimates that 3 persons could rewire Jasminder's house in 4 days. If
he uses 4 persons instead of three, how long should they take to complete the job?
Answers
Answered by
5
Step-by-step explanation:
it means that 3 person do work in 4 days
so 1 person take = 4/ 3 days
then if 4 person work it will take
4/3 * 4 = 16 / 3 days
if you want you can convert it to hours for simplify it