Math, asked by TheVAIBHAV13, 7 months ago

A contractor estimates that 3 persons could rewire Jasminder's house in 4 days. If
he uses 4 persons instead of three, how long should they take to complete the job?​

Answers

Answered by kunalchaprana143
5

Step-by-step explanation:

it means that 3 person do work in 4 days

so 1 person take = 4/ 3 days

then if 4 person work it will take

4/3 * 4 = 16 / 3 days

if you want you can convert it to hours for simplify it

Similar questions