Math, asked by nakshdhiman19, 7 hours ago

A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses
4 persons instead of three, how long should they take to complete the job?


pls answer fast

Answers

Answered by sidharthkumar887
1

Answer:the answer is 3 days pls mark me as genius

Step-by-step explanation:

Answered by Anonymous
1

Let the time taken to complete the job be x.

Here the number of persons and the number of days are in inverse proportion.

\therefore\frac{3}{4}=\frac{x}{4}

\Rightarrow\frac{4\times3}{4} = x

\Rightarrow\frac{12}{4} = x

⇒ x = 3

They will complete the job in 3 days.

please mark as brainliest

Attachments:
Similar questions