A contractor estimates that he will finish the road
construction project in 100 days by employing 50 men.
However, at the end of the 50th day, when as per his
estimation half the work should have been completed, he
finds that only 40% of his work is done.
(a) How many more days will be required to complete
the work?
(b) How many more men should he employ in order to
complete the work in time?
Answers
Answered by
0
Answer:
(a) 60 more days required to complete the work .
60 more men should he employ in order to complete the work in time.
Step-by-step explanation:
Hope it will help you
Similar questions