a contractor estimates that three persons could review this means a house in 4 days if he used for person instead of three how long should they take to complete the job
Attachments:
Answers
Answered by
0
Answer:
jfjffj Kristal disgust futuristic
mark me brain list
Attachments:
Answered by
0
According to the estimation in rewiring Jasminder's house
Number of persons required =3
Number of days required =4
So, to rewire a house by 1 person it will take 4×3=12 days
And to do job by 4 persons, days required =
4
12
=3 days