A contractor had to complete a project in 8 months. For that he employed 240 men. Due reasons, he had to finish the project two months earlier. How much more labour should he employ to finish the project in time?
Answers
Answered by
1
Answer:
two months= 60 mens
Step-by-step explanation:
1 mounth = 240/8
=30 men's
Answered by
1
Answer:
for 8months it require 240 mens
so according to the formula:
T1×Labour1=T2×labour2
8×240=6×l2
8×240/6= l2
l2=320mens