A contractor had to complete a project in 8 months. For that he employed 240 men. Due reasons, he had to finish the project two months earlier. How much more labour should he employ to finish the project in time?​

Answers

Answered by yashodamalvi677
1

Answer:

two months= 60 mens

Step-by-step explanation:

1 mounth = 240/8

=30 men's

Answered by chandniagrawal201
1

Answer:

for 8months it require 240 mens

so according to the formula:

T1×Labour1=T2×labour2

8×240=6×l2

8×240/6= l2

l2=320mens