A contractor has to build a wall in 50 days. He employs 50 men for the same. However, after 25 days the work is only 40% complete. How many more men need to be employed to complete the work 10 days before time?
Answers
Answered by
0
Answer:
75 men
Step-by-step explanation:
As 40% work by 50 men is completed in 25 days,
The whole work can be completed in 25*100/40=125/2 days
So 1 man, 1 day work=2/(125*50)=1/3125
50 men,25 days work=25*2/125=2/5,
The remaining work(=3/5) is to be completed by 50 men+ 'x' men in next 15 days (Total 40 days),
So 15 [ (2/125) + (x*1/3125) ] = 3/5
750+15x=1875,
x=75
hope it helps u......