A contractor has to finish a work in 20 days and employs 30 men on the job. If the
work is to be finished in 15 days, the number
of extramen to be employed is.
Answers
Answered by
7
Answer:
This should be simple:
Work load = Work done
Let x=additional men to finish the job
Assuming same work rate of 8hrs per day, thus, you can equate:
(30)(20) = (15)(30+x)
x=10 men