A contractor has two teams of workers: team a and team
b. team a can complete a job in 12 days and team b can do the same job in 36 days. team a starts working on the job and team b joins team a after four days. the team a withdraws after two more days. for how many more days should team b work to complete the job?
Answers
Answered by
46
Rate of team a = 1/12
Rate of team b = 1/36
Combined rate = 1/12 + 1/36 = 1/9
Fraction done in 4 days = 4x1/12 = 1/3
Remaining fraction = 1-1/3 = 2/3
Two days working together
Fraction done = 2x1/9 = 2/9
Remaining fraction = 2/3 – 2/9 = 4/9
Number of days it will take team b to complete the job = (4/9)/(1/36)
= 16 days
Rate of team b = 1/36
Combined rate = 1/12 + 1/36 = 1/9
Fraction done in 4 days = 4x1/12 = 1/3
Remaining fraction = 1-1/3 = 2/3
Two days working together
Fraction done = 2x1/9 = 2/9
Remaining fraction = 2/3 – 2/9 = 4/9
Number of days it will take team b to complete the job = (4/9)/(1/36)
= 16 days
Answered by
7
Ans. 16
Solution(*STEP BY STEP):
Let total worker in team A be x
Let total worker in team B be y
Given 12 x = 36 y
x = 3y
Per worker work done per day be W.
total work 36 × W × y
36Wy = 6 × Wx + MWy
M = 2 + Number of more days.
36 y = 18 y + My
M = 18y + My
M = 18
Hence 16 more days ( as M was 2 + number of more days)
Similar questions