A contractor has two teams of workers : team A and team B. Team A can complete a job in 8 days and team B can do the same job in 16 days. Team A starts working on the job and team B joins A after 2 days. Team A withdraws after 3 more days. Number of days for which team B should further work to complete the job is
Answers
Answered by
1
7 days is the answer
[16+2]-[8+3]
18-11
=7
[16+2]-[8+3]
18-11
=7
Similar questions
English,
7 months ago
Economy,
7 months ago
Social Sciences,
7 months ago
Social Sciences,
1 year ago
Science,
1 year ago
Science,
1 year ago