A Contractor
has
work force of
420
who finishes certain piece
ot work
q
months. How
many
mon must he
to
employ complete the
work in
in 7 months?"
in
Answers
Answered by
1
Men Time
420 9 months
x 7 months
As the number of workers is inversely proportional to time taken:
420×9=x×7⟹x=7420×9=540
∴ extra men needed: 540−420=120