A contractor promised finish a job in 40 days and and employed hundred men Aandhi job after 35 days he employed 100 more men to finish the job in time had he not extra engaged men how many more day the work would have taken to be finished
Answers
Answered by
0
Answer:
5 days
Step-by-step explanation:
100 men scheduled to finish a piece of work in 40 days
After 35 days 100 more men were engaged to finish the work on time.
This means 200 men finish the remaining work in 5 days.
100 men would have taken 200 * 5 / 100 = 10 days to finish the remaining work.
Extra days taken by 100 men would be 10-5 = 5days