A contractor promised to build a road 16 km. long in 150 days and put 224 men on the job.

After 84 days he found that only 7 km of the road was constructed. How many additional

men should he employ to finish the work 3 days earlier ? Step by step calculation​

Answers

Answered by prakriti12325
8

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length

of the road has been made . How many more men should he emply so that the work many be complete in time ?

answer 30