A contractor requires 42 labour’s to whitewash a building in 63 days. In how to how many days will the building be whitewashed if 7 more labour’s join the work ?
Answers
Answered by
3
Answer:-
54 Days
Step-by-step explanation:
THESE are in inverse proportion so
In 42 Workers||NOW 42+7
TIME-63DAYS||TIME X
so,42×63=49×X
X=42×63/49=54 Days.Answer