A contractor takes a contract of a work for 40 days and initially he appointed 100 men on the job. After 35 days he appointed 100 more person on the job and finished the work on time. If he doesn't appoints more workers on a job the how many days work will take to complete from actual time?
Answers
Answered by
0
Answer:
5 MORE DAYS
Step-by-step explanation:
last five days, 200 men worked to complete the work
if only 100 men worked, (only half) double time would be taken, so instead of 40, 45 days would be taken