A contractor takes a contract to build a stadium with the 430 men in 6 month later on he was asked to complete the work in 5 month how many more men mom and should he employed
Answers
Answered by
8
Solutions :-
We have,
430 men can build a stadium in 6 months
So, we can also write it as,
430 men = 6 months
Now,
Let the x men can build the same stadium in 5 months.
So, we can also write it as,
x men = 5 months
A/q
=> x × 5 = 430 × 6
=> 5x = 2580
=> x = 2580/5 = 516
Hence,
516 men can complete the work in 5 months.