A contractor takes a contract to build a stadium with the 430 men in 6 month later on he was asked to complete the work in 5 month how many more men mom and should he employed

Answers

Answered by Anonymous
8

Solutions :-




We have,



430 men can build a stadium in 6 months



So, we can also write it as,



430 men = 6 months




Now,



Let the x men can build the same stadium in 5 months.



So, we can also write it as,



x men = 5 months





A/q



=> x × 5 = 430 × 6


=> 5x = 2580


=> x = 2580/5 = 516






Hence,



516 men can complete the work in 5 months.