A contractor takes a contract to construct 800kms road in 40days and employ 100 workers for it.if he wants to complete the work in 30 days, how many workers will he need

Answers

Answered by kumarsanjay125
0
let the required worker = X
More length of road ,more worker (direct proportion)
More days, Less workers. (indirect proportion)
Length of road 800 : 800
Days 30 : 40 since indirect proportion)
Worker X : 100
800*30*100=800*40*X
X=(800*100*40)/(800*30)
=400/3
=133.33 =approx 134 worker

Thanks