a contractor, took a contract of building a panchayat bhawan in 8 months. The contractor had 210 workers. He was asked to complete the work in 6 months, then how many more workers he will have to employee.
Answers
Answered by
0
Answer:
280
Step-by-step explanation:
it is inversely proportio
210×8=6×z
z=210×8÷6
z=280 worker