Math, asked by sandhyagupta1, 6 months ago

a contractor, took a contract of building a panchayat bhawan in 8 months. The contractor had 210 workers. He was asked to complete the work in 6 months, then how many more workers he will have to employee.​

Answers

Answered by jadhavprathamesh2004
0

Answer:

280

Step-by-step explanation:

it is inversely proportio

210×8=6×z

z=210×8÷6

z=280 worker