Math, asked by roshan6065, 1 year ago

A contractor under took a piece of work in 25
days. He employed 500 men. After 10 days he
employed 200 more men and thus work be
completed in time. if extra men are not been
employed. How many days behind the work
have done​

Answers

Answered by DevendraLal
2

Given:

A contractor undertook a piece of work in 25  days

To Find:

How many days behind the work  have done.

Solution:

1) After the 10 days work 200 more men were employed to complete the work on time.

2) Let the time taken by the 500 men to complete the remaining work after ten days is X.

3) The work done by the men will be the same in both cases,

• 500×X = 700×15

• X = 700×15/500

• X = 7×3

• X = 21

If more men were not employed then they will take 21-15 = 6 days extra to complete the same work.

6 days behind the work is about to finish.