Math, asked by Boigou1, 1 year ago

A contractor undertakes to build a road 12 km long in 350 days and employs 45 men. At the end of 200 days he finds that 9/2 km of the road have been completed. How many additional men must he employ inorder to get the work finished in time?

Answers

Answered by Lakshay02
16
here is your answer


4.5 km in 200 days by 45 men
now remaining 7.5 km in 150 days by 45+x men
200*45/4.5 =(45+x)*150/7.5
on solving this we get x=55 so 55 men extra are required
 

Lakshay02: please mark as brainlist
Answered by romabaithiyam
14

A contractor  undertake to build a road 12k long in 350 days and employs 45men .at the end of 200 days he finds that 4 and half km of the road have been completed .how many additional men must he now employ in order to get  the work finished in time?