Math, asked by lovely4942, 1 year ago

A contractor undertakes to build a road 12 km long in 350 days and employs 45 men,. At the end of 200 days he finds that 4by1/2km of the road have been completed. How many additional men must he now employ in order to get the worked finished in time?

Answers

Answered by divergent07
2
here is the answer ...55 men more needed