.A contractor undertakes to build a wall
1000 m long in 50 days. He employs 56 men,
but at the end of 27 days, he finds that only
448 m of wall is built. How many extra men
must the contractor employ so that the wall is
completed in time?
Answers
Answer:
Step-by-step explanation:
Wall Built = 448m; Time Taken = 27 days; Men working = 56 men
Wall built by 56 men in 1 day = 448/27m
Wall built by 1 man in 1 day = 448/(27x56) = 56/189m
Now,
Wall left to be built = 552m; Time left = 23 days; Total men required to complete the rest of work = x
Wall built by x no. of men in 1 day = 56x/189m
Wall built by x no. of men in 23 days =(56*23)x/189 = 1288x/189
Thus,
1288x/189 = 552 (As x no. of men have to build 552m of wall)
1288x = 104328
x = 104328/1288
x = 81 men
Therefore, extra men required = 81-56
= 25 men
Total time given =50 days.
Wall to be build =1000 m
On 27th day 448 m of wall is built,
Remaining days =23, remaining wall =552 m.
In 27 days, 448 m of wall is built by 56 employee.
In 1 day 1 m of wall is built by 56×27/448 employee
In 23 days, 552 m of wall is built by x employee.
So, no. of employee required =81−56=25.