A contractor undertakes to complete a work in 20days. He employs 30labourers on this job.How many more labourers would he employ to complete the work in 15days?
Answers
Answered by
0
Answer:
in which classsssssssss
Answered by
1
Answer:
Simply no of persons are inversely proportional to days of work. Therefore if no of days are reduced by 3/4th then no of person will be 4/3rd of the original persons.
Therefore 30*4/3=40 ,10 more men he should employ
Step-by-step explanation: