a contractor undertakes to construct a road in 20 days and engages 12 workers. After 16 days , he finds that only 2/3 of his has been completed. how many more workers should he employ in order to finish the job?
Answers
Answered by
3
60 more workers should he employ in order to finish the job
Similar questions