Math, asked by rohanjohn, 1 year ago

a contractor undertakes to construct a road in 20 days and engages 12 workers. After 16 days , he finds that only 2/3 of his has benn completed. hw many more workers should he employ in order to finish the job

Answers

Answered by Anonymous
7
please mark it as a brainliest answer