A contractor undertakes to construct a road in 20 days and engages 12 workers. After 16 days, he finds that only 2/3 part of the work has been done. How many more workers should be now engage in order to finish the job in time?
Answers
Answer:
PLEASE MARK ME AS BRAINLIEST
Explanation:
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contract
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:Work output per person per day
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:Work output per person per day(((5/8)/20)/16)
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:Work output per person per day(((5/8)/20)/16)Work left to be completed at end of 12th day = (1–5/8) = 3/8
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:Work output per person per day(((5/8)/20)/16)Work left to be completed at end of 12th day = (1–5/8) = 3/8No of labour required to complete work in day = (3/8) ÷ (((5/8)/20)/16)
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:Work output per person per day(((5/8)/20)/16)Work left to be completed at end of 12th day = (1–5/8) = 3/8No of labour required to complete work in day = (3/8) ÷ (((5/8)/20)/16)No of labour required to complete work in 4 days = (3/8) ÷ (((5/8)/20)/16) ÷ 4 = 48 labourers
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 5/8th of the road had been constructed.To complete the work in stipulated time the number of extra labours required is?28 extra workers (48 total) needed in next 4 days to comply work as per original contractMethod:Work output per person per day(((5/8)/20)/16)Work left to be completed at end of 12th day = (1–5/8) = 3/8No of labour required to complete work in day = (3/8) ÷ (((5/8)/20)/16)No of labour required to complete work in 4 days = (3/8) ÷ (((5/8)/20)/16) ÷ 4 = 48 labourersExtra workers required = 48–20=28 extra workers (labourers)
A contractor undertakes to construct a road in 20 days and engages 12 workers. After 16 days, he finds that only 2/3 part of the work has been done. How many more workers should be now engage in order to finish the job in time?
From the Question,
Remaining number of days = 20 - 16 = 4
•°• Number of workers required to complete 2/3 part of work in 16 days = 12