A contractor undertakes to construct a road in 20 days and engages 12 workers After 16 days he finds that only part of the work has been done. How many more workers should he now engage in order to finish the job in time? ​

Attachments:

Answers

Answered by funwithstudies2304
1

Answer:

He Must Engage 4 more workers