Math, asked by asdfghjk, 1 year ago

A contractor undertakes to dig a canal.6 km long,in 35 days and employed 90 men.He finds that after 20 days only 2km of canal have been completed.How many more men must be employed to finish the work in time?

Answers

Answered by josimagic
45

Answer:

150 men must be employed to finish the work in time

Step-by-step explanation:

m1 person can do w1 works in d1 days and m2 person can do w2 works in d2 days then we have a generated formula in their relationship

\frac{m1d1}{w1}=\frac{m2d2}{w2}

Let the work be to dig a canal.6 km long,

work, w = 6

Also 'x' be the people wanted to finish the work in time

first case

After 20 days 90 men completed 2 km long

w1 = 2, m1 = 90 and d1 =20

Second case

The remaining work be 6 - 2 = 4

w2 = 4, m2 = 90 + x and d2 = 35 - 20 = 15

To find x

By using the formula,

\frac{90*20}{2}=\frac{(90+x)15}{4}

90*20=\frac{(90+x)15}{2}

90x20x2=(90+x)15

x = 150

Therefore the number of people wanted to finish the work = 150

Similar questions