Math, asked by tokaians, 1 year ago

A contractor undertakes to dig a canal,6kilometre long in 35 days and employed 90 men. He finds that after 20 days only 2 km of canal have been completed.how many more men must be employed to finish the work in time?
FAST PLZ

Answers

Answered by kvnmurty
13
In 20 days 2000 meters work is done by 90 men.
So work capacity of 1 man =  2000 m  / (20 days * 90 men)  = 10/9 meter per day per man

Work remaining = 6 000 m - 2000 m = 4000 m
Days remaining = 35 days - 20 days = 15 days
One man can do in 15 days,  work = 10/9 * 15  = 50/3  meters
Number of men needed  = work remains / work capacity of one man
                         = 4000 / (50/3)  =    240  men needed

tokaians: as the question says
Similar questions