A contractor undertook a contract to complete a part of a stadium in 9 months with
a work-force of 560 men. later on, it was required to complete the job in 7 months.
How many extra men would he employ?
Answers
Answered by
7
Answer:
436
Step-by-step explanation:
let take x = extra men would he employed
months. men
9. 560
7. x
cross multiply *<- this is the symbol for multiply.
(9*x) = (560*7)
9x. = (3920)
x. = 3920/9
[ / <- this slash is the symbol of division]
x. = 435.5555555556
round it
x. = 436
560 - 436 = 124
therefore,
124 extramen would he employed.