A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 1/5th of the project work had been completed. To complete the work in time (i.E,in rest days) minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

Answers

Answered by mirzamohsin110
0

Answer:

35 more workers required for remaining 40 days to finish project work.