A contractor undertook to build a road in 200 days he employed 140 man after 60 days he found that only one by four of the work would be billed how many additional men should be employed to complete the work in time

Answers

Answered by aman240292
7

Step-by-step explanation:

Pls find the attached file for ur reference.

Attachments:
Answered by gchandracommercial
2

Answer:

40 men