A contractor undertook to built a road in 100 days he employed 110 men.After 45 days ,he found that 1/4 work done , how many men required to to work in time

Answers

Answered by haridasan85
1

Answer:

men Days. Completion

110. 45. I/4

x. 55..... 3/4

x = Total men required

x = 3/4x4 / Ix45/55x110=270

Extra men=270-110 = 160