A contractor undertook to com-
plete a project in 90 days and
employed 60 men on it. After 60
days, he found that 3/4 of the
work has already been com-
pleted. How many men can he
discharge so that the project
may be completed exactly on
time?
Answers
Answered by
3
Answer:
20 men's will be discharged
Step-by-step explanation:
if 90days for 60 men
then for 60 days how many men's (x)
90/60= 60/x
x= 60×60/90
x= 3600/90
x= 40
for completing work in 60 days only 40 men required
we have 60 men
then 60-40= 20
20 men will be discharged