A contractor undertook to dig a canal in 72 days. He employed 70 men to dig it. How many extra Men should he employ in order to complete the work in 56 days?

Answers

Answered by emmanenisanthoshrao
11

Answer:

70 men can dig a canal= 72 days

no of men to dig in one day= 70×72=5040

no of men required to dig in 56 days= 5040/56=90

extra men required= 90-70=20