A contractor undertook to dig a canal in 72 days. He employed 70 men to dig it. How many extra Men should he employ in order to complete the work in 56 days?
Answers
Answered by
11
Answer:
70 men can dig a canal= 72 days
no of men to dig in one day= 70×72=5040
no of men required to dig in 56 days= 5040/56=90
extra men required= 90-70=20