a contractor undertook to do a work in 60 days he employed 50 men after 40 days he found that only half of the work had been done how many additional man he should employ so that work may be done in time
Anonymous:
___k off
Answers
Answered by
2
Answer:
Step-by-step explanation:
He should hire 55 more men
Answered by
5
50 additional men are required.
Step-by-step explanation:
Consider the provided information.
half of the work had been done in 40 days.
So, half of the work needs to be done in 60-40 = 20 days.
In 40 days work is done by 50 men.
That means in 1 day work is done by: 50×40
In 20 days work is done by:
So they need total 100 employees but they already has 50.
So the additional men required are: 100-50=50.
Hence, 50 additional men are required.
#Learn more
A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?
https://brainly.in/question/4046974
Similar questions