Math, asked by jitendra785864, 1 year ago

a contractor undertook to do a work in 60 days he employed 50 men after 40 days he found that only half of the work had been done how many additional man he should employ so that work may be done in time


Anonymous: ___k off

Answers

Answered by ajadams
2

Answer:

Step-by-step explanation:

He should hire 55 more men

Answered by FelisFelis
5

50 additional men are required.

Step-by-step explanation:

Consider the provided information.

half of the work had been done in 40 days.

So, half of the work needs to be done in 60-40 = 20 days.

In 40 days \frac{1}{2} work is done by 50 men.

That means in 1 day \frac{1}{2} work is done by: 50×40

In 20 days  \frac{1}{2} work is done by: =\frac{50\times40}{20} =100

So they need total 100 employees but they already has 50.

So the additional men required are: 100-50=50.

Hence, 50 additional men are required.