A contractor undertook to do work in 60 days . He employed 50 workers to carry job,but after 40 days he found half work done. Now how many more workers should he employee to go finish workin time

Answers

Answered by IronHulk
0

Answer:

25. he should employ another 25 workers.

Step-by-step explanation:

There is a inverse relation in the problem.

50 can complete half job in 40 days

to complete work of 60 days I.e remaining 20 days work. they need to work 50% extra for that we need 50% extra workers. so total we need 75 workers I.e 25 extra.

Mathematical proof

50 workers = 40 days(half work)

how many workers to complete another half?I.e total work of 60 days...

= Since it is inversely related

X= 50×60÷40=75. therefore 75-50=25 extra workers....