A contractor undertook to finish a
cbork in 92 days and employed
110 men. After 48 days, he found
that he had already done 3/5
of the work, the number of
men he can withdraw so that the
work may be finished in time
is :

Answers

Answered by Gurujia1
0

Answer:

Step-by-step explanation:

110×48/3. =x×44/2

X=80

Than

Withdraw men is