A contractor undertook to finish a
cbork in 92 days and employed
110 men. After 48 days, he found
that he had already done 3/5
of the work, the number of
men he can withdraw so that the
work may be finished in time
is :
Answers
Answered by
0
Answer:
Step-by-step explanation:
110×48/3. =x×44/2
X=80
Than
Withdraw men is
110-80=30