A contractor who had a work force of 560 persons Have complete a portion of a stadium in 9 months . He was asked to complete in 7 months. How many extra persons he had to employ ?
Answers
Answered by
6
560 persons -----------9 months
? -----------7 months
they are in inverse proportion
so
560 x 9 / 7 =720
therefore
no. of persons required to complete work in 7 months = 720 persons