A contractor who had a work force of 630 man , undertook to complete a portion of a stadium in 14 months. He was asked to complete this job in 9 months.
How many extra persons he had to employ?
Answers
Answer:
The number of extra people required is 350.
Step-by-step explanation:
Given,
Let the number of people required to complete a job in 9 months be 'x'.
Number of persons that complete work in 14 months = 630
The number of persons required to complete the work in 9 months is
Therefore, the extra persons required to complete the work = 980 - 630 = 350.
Hence, the extra person contractor had to employ is 350.
To learn more about work, click on the link below:
https://brainly.in/question/12763041
To learn more about work and person concept, click on the link below:
https://brainly.in/question/50489522
#SPJ2
Answer:
The correct answer to this question is 350 persons.
Step-by-step explanation:
Given: A contractor who had a work force of 630 man , undertook to complete a portion of a stadium in 14 months. He was asked to complete this job in 9 months.
To find: How many extra persons he had to employ
calculation:
Let the number of people required to complete a job in 9 months be 'x'.
Number of persons that complete work in 14 months = 630
The number of persons required to complete the work in 9 months
=
Therefore the value of 'x' is 980 person.
Now, the extra persons required to complete the work
=
So, the extra person contractor had to employ is 350.