A contractor who had a work force of 630 person, undertook to complete a portion of a stadium in 14 months. He was asked to complete the job in 9 months. How many extra person had he to employ?
Answers
Answered by
27
★Answer
350 extra person had to be employed
★Step by step explanation
No. of people complete a portion of stadium in 14 months = 630
so,
Let no. of people required to complete the whole stadium job in 9 months = X
ATQ, (on inverse proportion)
A1/A2 = B2/B1
9/14 = 630/X
9x = 630×14
x = 630×14/9
x = 980
therefore,
extra person needed are:
= 980-630
= 350